Delhi HC lets Noida airport operator encash Tata Projects bank guarantees

The court said the guarantees are separate from the construction dispute and Tata Projects could recover the money later if it proves the encashment was wrongful.

Delhi HC lets Noida airport operator encash Tata Projects bank guarantees – India Martijn Stoof

The Delhi High Court has rejected Tata Projects’ plea to stop the operator of Noida International Airport from encashing three bank guarantees, leaving the construction dispute to be resolved through arbitration. The ruling was delivered on 26 November by a bench led by Justice Tushar Rao Gedela.

The court said the guarantees were separate from the main contract dispute between Tata Projects and Yamuna International Airport Pvt Ltd (YIAPL). It found no case that the encashment would cause an unrecoverable loss: if Tata Projects later proves that the guarantees were wrongly encashed, the money could be recovered, the court said.

The decision concerns work on the first phase of Noida International Airport. YIAPL awarded Tata Projects two construction contracts in June 2022, together worth ₹4,582.02 crore. The ruling sets the immediate position on the guarantees but does not decide which side is responsible for the underlying payment and construction claims.

What is the dispute about?

The contracts covered the terminal and related works, valued at ₹1,892.42 crore, and airside, landside, utilities and related works, valued at ₹2,689.60 crore. The original completion deadline was 23 November 2024. After payment and other disputes arose, Tata Projects claimed about ₹1,112.87 crore, while YIAPL made counterclaims of ₹436.72 crore.

The companies signed a settlement agreement on 25 February 2026. Under it, Tata Projects agreed to finish the remaining work by 31 July 2026, with a 60-day extension to 29 September 2026. YIAPL alleged that Tata Projects missed the revised deadlines and encashed the guarantees.

Tata Projects told the court that YIAPL had not made payments agreed in the settlement and that the company had spent ₹167.68 crore of its own funds from June to October 2026. It attributed delays to site access, work dependent on other agencies, pending changes and additional work. It said 93.5% of the first package and 95.1% of the second had been completed.

What happens next?

The high court declined to intervene in the encashment, saying the construction dispute would have to be settled in arbitration. The ruling does not resolve the parties’ competing claims over payments, delays or performance. Responses from Tata Projects and YIAPL to Mint’s email queries were awaited.